For a 1,000 sq ft built-up house of G+1 to G+3 in M20 concrete, the thumb rules give about 400 bags of cement (0.4 per sq ft), 1,800 cft of sand (1.8 per sq ft) and 1,350 cft of coarse aggregate (1.35 per sq ft), plus 4,000 kg of steel. Treat them as planning figures, not a design.
How many bags of cement, how much sand and how much coarse aggregate does a 1,000 sq ft house need? The planning thumb rules, how they change with the number of floors, and where they stop being reliable.
For G+1 to G+3 houses in M20 concrete, NirmanShastra's StructurePro starts from these planning values. They are per sq ft of built-up area, meaning the total across all floors.
| Material | Per sq ft of built-up area | For 1,000 sq ft |
|---|---|---|
| Cement (50 kg bags) | 0.4 bag | 400 bags |
| Sand | 1.8 cft | 1,800 cft (about 51 m³) |
| Coarse aggregate | 1.35 cft | 1,350 cft (about 38.2 m³) |
| Steel | 4 kg | 4,000 kg |
| Binding wire | 12 kg per tonne of steel | 48 kg |
The thumb rule is set for G+1 to G+3. The estimator applies a factor outside that range. Per 1,000 sq ft of built-up area in M20 concrete:
| Floors | Factor | Cement (bags) | Steel (kg) | Sand (cft) | Aggregate (cft) |
|---|---|---|---|---|---|
| Ground floor only | 0.85 | 340 | 3,400 | 1,530 | 1,148 |
| G+1 to G+3 | 1.00 | 400 | 4,000 | 1,800 | 1,350 |
| G+4 | 1.08 | 432 | 4,320 | 1,944 | 1,458 |
| G+5 | 1.12 | 448 | 4,480 | 2,016 | 1,512 |
The values scale in proportion to built-up area. A 1,500 sq ft G+1 house needs about 600 bags of cement, 6,000 kg of steel, 2,700 cft of sand and 2,025 cft of coarse aggregate.
For one slab, beam or column, work from concrete volume instead. M20 concrete needs about 8.07 bags of 50 kg cement per cubic metre (IS 456:2000), so a 20 m³ slab needs roughly 161 bags. The free Concrete Mix Ratio Calculator does this for any volume, and how to verify a contractor's quote against IS 456 shows the cross-check step by step.
For a quantity schedule built on your own area, floors, state and site condition, use StructurePro. The glossary explains terms such as built-up area, G+1 and M20.
About 400 bags of 50 kg cement, from the thumb rule of 0.4 bag per sq ft of built-up area for G+1 to G+3 buildings in M20 concrete.
About 1,800 cft, which is roughly 51 m³, at 1.8 cft per sq ft of built-up area.
About 1,350 cft, which is roughly 38.2 m³, at 1.35 cft per sq ft of built-up area.
Yes. Per 1,000 sq ft of built-up area, a ground-floor-only house uses about 340 bags of cement, G+1 to G+3 uses 400, G+4 uses 432 and G+5 uses 448.
The total built-up area across all floors, not the plot size or one floor. A G+1 house with 500 sq ft on each floor has 1,000 sq ft of built-up area.
Use the per-cubic-metre figure: M20 concrete needs about 8.07 bags of 50 kg cement per m³, so a 20 m³ pour needs roughly 161 bags.